Slab Preparation & Floors

On Monday Feb 4th the wall forms were striped, and the underground plumbing was installed.  The foundation coating was completed on Monday evening.  On Tuesday plumbing inspections were completed, forms were removed from the site and equipment was delivered for the slab preparation. The balance of the week was devoted to preparing the engineered footings, installing the concrete reinforcing bar, electrical conduit and radon gas vent.  Inspections were completed on Friday March 8 and floors were poured on Saturday March 9th