Inspections ere completed on Monday Feb 25th, and the footings were poured at 1:00 PM. On Tuesday the forms were stripped and the concrete coring for the new window in the back wall was completed. Wall forms were set on Wednesday & Thursday, inspections were completed and the walls were poured Friday March 1st.